Bombardier Recreational Products

Bombardier, an outboard motor and recreational product manufacturer, required the reconfiguration of 408,000 square feet of a building Berghammer originally built for a previous owner. It was necessary to coordinate the removal of equipment from the previous owner with the installation of Bombardier machinery. Berghammer’s project team implemented an aggressive schedule in order to have the plant up and running when the first materials for production arrived. The team worked closely with the construction manager from Canada and completed the project within the 16 week time frame.

Location: Sturtevant, Wisconsin
Duration: 4 months
Scope: 600,000 Square Feet